Home » PMI » CAPM v.2 » Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?
Which of the following is the process of identifying the specific actions to be performed to produce the project deliverables?
A. Estimate Activity Durations
B. Sequence Activities
C. Define Activities
D. Activity Attributes
Correct Answer: C
Explanation/Reference:
Explanation:
Process: 6.2 Define Activities
Definition: The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Key Benefit: The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
Inputs
1.Schedule management plan
2.Scope baseline
3.Enterprise environmental factors
4.Organizational process assets
Tools & Techniques
1.Decomposition
2.Rolling wave planning
3.Expert judgment
Outputs
1. Activity list
2. Activity attributes
3.Milestone list