Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?

Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?
A. Gantt chart
B. Project schedule network diagram
C. Project milestone list
D. Activity list