Home » PMI » CAPM v.2 » The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
A. Continuous improvement.
B. Predictive planning.
C. Progressive elaboration.
D. Quality assurance.
Correct Answer: C
Explanation/Reference: