The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
A. Monitor Communications
B. Plan Communications Management
C. Manage Communications
D. Manage Stakeholder Engagement
Correct Answer: C
Explanation/Reference:
Reference: https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=4&ved=2ahUKEwityYzPzNThAhUH6qQKHR77AboQFjADegQIARAC&url=https%3A%2F%2Fpeople.eecs.ku.edu%2F~hossein%2F811%2FLectures%2Fchapter-10.pptx&usg=AOvVaw0B7ldXssetUgjbMWGxmkXp