Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
A. Estimate at completion
B. Cost performance
C. Schedule performance
D. To-complete performance