How long will it take to complete the project?

Given the following information:
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A. Activity D follows Activity C.
How long will it take to complete the project?
A. 8 weeks
B. 9 weeks
C. 10 weeks
D. 11 weeks