Home » PMI » CAPM v.2 » Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?
Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?
A. Communications methods
B. Reporting systems
C. Forecasting methods
D. Variance analysis
Correct Answer: B
Explanation/Reference:
Explanation:
Reporting Systems. Facilities, processes, and procedures used to generate or consolidate reports from one or more information management systems and facilitate report distribution to the project stakeholders.