Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?
A. Recommended corrective actions
B. Recommended preventive actions
C. Risk audits
D. Risk reassessments
Correct Answer: B
Explanation/Reference:
Explanation:
11.6.3.2Change Requests
Implementing contingency plans or workarounds sometimes results in a change request. Change requests are prepared and submitted to the Perform Integrated
Change Control process (Section 4.5). Change requests can include recommended corrective and preventive actions as well.
Recommended corrective actions. These are activities that realign the performance of the project work with the project management plan. They include contingency plans and workarounds. The latter are responses that were not initially planned, but are required to deal with emerging risks that were previously unidentified or accepted passively.
Recommended preventive actions. These are activities that ensure that future performance of the project work is aligned with the project management plan.