Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?
A. Configuration definition, configuration status accounting, configuration monitoring and control
B. Configuration identification, configuration status accounting, configuration verification and audit
C. Configuration identification, configuration status reporting, configuration verification and audit
D. Configuration definition, configuration status reporting, configuration monitoring and Control
Correct Answer: B
Explanation/Reference:
Explanation:
Configuration control is focused on the specification of both the deliverables and the processes; while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.
Some of the configuration management activities included in the Perform Integrated Change Control process are as follows:
Configuration identification. Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.
Configuration status accounting. Information is recorded and reported as to when appropriate data about the configuration item should be provided. This information includes a listing of approved configuration identification, status of proposed changes to the configuration, and the implementation status of approved changes.
Configuration verification and audit. Configuration verification and configuration audits ensure the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented. This ensures the functional requirements defined in the configuration documentation have been met.