Home » PMI » CAPM v.2 » When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process:
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process:
A. Develop Schedule
B. Define Activities
C. Define Scope
D. Collect Requirements
Correct Answer: B
Explanation/Reference:
In agile projects, DECOMPOSITION is Tool and technique of define activities, create WBS. You have subdivided the work package into smaller manageable components of schedule activities which is decomposition. Decomposition was used to create WBS process, if u further decompose WBS package you get schedule of activities.
Rolling Wave Planning is one of the techniques in the ‘Define Activities’ process under Project Time Management.
Download Printable PDF. VALID exam to help you PASS.
|
|