During a risk assessment, results show that a fire in one of the company’s datacenters could cost up to $20 million in equipment damages and lost revenue. As a result, the company insures the datacenter for up to $20 million damages for the cost of $30,000 a year. Which of the following risk response techniques has the company chosen?
A. Transference
B. Avoidance
C. Mitigation
D. Acceptance