For a critical project, a new team has been formed from various departments.

For a critical project, a new team has been formed from various departments. The project manager should start team building by:
A. Creating a project charter, documenting roles and responsibilities of each member, and sending it to the team members.
B. Taking the team offsite for icebreaker sessions and other activities to ensure team members get to know each other.
C. Assembling the team and discussing roles and responsibilities of each member on the team.
D. Assembling the team and asking the members to achieve a milestone in a small iteration.