Team velocity is used to:
A. Measure the percentage of features completed.
B. Judge productivity within the iteration.
C. Predict schedules for mature teams.
D. Give feedback on delivered value.
Team velocity is used to:
A. Measure the percentage of features completed.
B. Judge productivity within the iteration.
C. Predict schedules for mature teams.
D. Give feedback on delivered value.
Avg team velocity is used in forecasting long-term schedule.
Yes, answer is C – Predict schedules for mature teams
Velocity is a measurement of productivity within an iteration. Reaching a sustainable pace is part and parcel of this.
But, yes, the correct answer is “C”. Forgot to add this.
By knowing the velocity, Product Owner calculates how many sprints are needed to complete the approved features and hence predict schedules for mature teams is right answer