Which technique is used by a project team to estimate the amount of work that can be done per iteration?
A. Velocity measurement
B. Relative prioritization
C. Planning Poker
D. Release planning
Which technique is used by a project team to estimate the amount of work that can be done per iteration?
A. Velocity measurement
B. Relative prioritization
C. Planning Poker
D. Release planning
Answer is D
It’s a tricky question. Dont get confused with Planning Poker, PP is used to estimate the story points for a story by team members in iteration planning. Estimate for iteration will be done during Release Planning by senior team