However, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed.

Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can inferthat:


A. Work was removed from the Product Backlog.
B. Work was added to the Product Backlog.
C. The team’s velocity increased.
D. The team’s velocity decreased.