Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can inferthat:
A. Work was removed from the Product Backlog.
B. Work was added to the Product Backlog.
C. The team’s velocity increased.
D. The team’s velocity decreased.