On a team new to Scrum, two team members are disrupting the daily standup with a side conversation. The ScrumMaster should:
A. wait until the standup is over and then talk to the disruptive team members.
B. immediately intervene to remedy the disruptive situation.
C. record the issue and then raise the issue at the Sprint Retrospective.
D. wait for the empowered, self-organizing team to resolve the issue.

Download Printable PDF. VALID exam to help you PASS.

3 thoughts on “On a team new to Scrum, two team members are disrupting the daily standup with a side conversation.

  1. If I were taking the PSM exam, I would choose D, as the argument of a self-organized team would prevail. However, for the ACP exam, I’d go for the letter B, onde the team is “new” and may not be able to apply the rules properly yet. So, as a project leader it would be more productive to intervenee at the forming stage. It would be different if the team were already in the norming or performing stages.

  2. On a team new to Scrum, two team members are disrupting the daily standup with a side conversation. The ScrumMaster should:
    As per PMchallenge Answer Questions the answer is A. wait until the standup is over and then talk to the disruptive team members.

  3. I believe this should be ‘D’.
    D. wait for the empowered, self-organizing team to resolve the issue as the job of the Scrum Master is there only to facilitate.