How to introduce the new process. The project manager’s initial plan should be to:

A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process. The project manager’s initial plan should be to:
A. Institute daily standup meetings immediately.
B. Communicate the Agile Manifesto to the team.
C. Balance teaching principles with Agile practices.
D. Rate the team’s progress in learning new methods.