In Agile risk management, a risk burndown chart is best used to:

In Agile risk management, a risk burndown chart is best used to:
A. Qualitatively analyze the probability of a risk occurring.
B. Track progress on risk reduction of technical risks.
C. Document the external risks that could impact the project.
D. Illustrate the project risk profile and new and changing risks.