What is the best first step the business analyst should take regarding this risk?

A business analyst has identified a new risk in an Agile project. What is the best first step the business analyst should take regarding this risk?
A. Call a meeting with the project manager and senior management to determine how the risk will be managed.
B. Email the project manager and add it to the risk register so that it is discussed during the next daily standup.
C. Add the risk in a clearly visible location and ensure it is discussed after the next daily stand up.
D. Call an immediate meeting with all team members to discuss the newly identified risk.