The following chart lists stories for a release of an Agile project:
If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
A. 3
B. 4
C. 5
D. 7
The following chart lists stories for a release of an Agile project:
If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
A. 3
B. 4
C. 5
D. 7
Rajasrinivas Srinivas Regulavalasa , I think your math is wrong.
The correct answer is “B”. Total story points is 31. 31 / 10 = 3.1. Round up to 4.
The given answer is wrong. Sum up all the story points counts to 30 and when velocity is 10, number of iteations required are 30/10 =3