Following chart lists stories for a release of an Agile project;
If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team’s velocity?
A. 9
B. 10
C. 12
D. 15
Following chart lists stories for a release of an Agile project;
If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team’s velocity?
A. 9
B. 10
C. 12
D. 15
This is perfecty right answer. There is no % completion in Agile. IT has to be fully completed and demo ready.