You are a resource manager and manage a project with Project Server 2013 and Project Professional 2013. Without notice, one of your key resources decides to take a leave of absence for 30 days. You need to account for the…

You work in an organization that uses Project Online. Project managers have full control over resource assignments. You work in the Project Management Office (PMO) and discover that two of your critical resources are overallocated in the Resource Center for…

You are a project administrator and are implementing Project Server 2013 for a large organization. You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure. You need…

You are a project manager who uses Project Server 2013 and Project Professional 2013. You are managing a project that has already begun. A new change request has been pre- approved, and the director wants to understand the impact to…

You are a Project Server 2013 administrator, and you support the Project Management Office (PMO) project managers who need to estimate project hours and costs without knowing the specific resource names. There are options available to accommodate this request when…

You are a project manager for an organization that uses Project Server 2013. You are evaluating resource information in the Resource Center. The following information is presented to you on the Resource Availability page: You need to determine if a…

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a project with common tasks for which many resources on your team can be used. Because your resources have responsibilities outside of the project,…

You are a project manager who uses Project Online. You build and publish a resource plan for your project. You check the resource demand in the Resource Availability screen. You do not see the correct demand as defined in the…

You are a project manager for an organization that uses Project Online. You create a resource plan to provide high level resource demand during the portfolio intake and selection process. Your project is now selected for detailed planning. You complete…

You are a project manager, and your organization uses Project Server 2013 with an enterprise resource pool. After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that…