You work in the Project Management Office (PMO) for an organization that uses Project Server 2013. Team members enter task updates in Project Web App (PWA), and project managers review these updates in PWA. You discover that team members enter…

You are a team member in an organization that uses Project Server 2013. Each week you report progress on multiple projects that are managed as Microsoft SharePoint task lists. You need to update task progress on multiple projects from one…

You are a project manager for an organization that uses Project Server 2013. You create a complex schedule that has many segments which are divided by your organization’s departments and external vendors. The duration of the schedule is 18 months.…

You are an administrator in an organization that uses Project Server 2013. Single entry mode is disabled. Resources use the Tasks page in Project Web App (PWA) to report task progress. You need to ensure that resources have the ability…

You are a team member for an organization that assigns your tasks on schedules. Single-entry mode is not enabled. At the end of the week, you submit your timesheet in Project Server 2013. Default security settings are enabled. However, a…

Your organization uses Project Server 2013. Your environment’s default task mode is auto scheduled. Your environment allows manually scheduled tasks to be displayed in Project Web App (PWA). You create a detailed enterprise project with resources assigned to auto scheduled…

You are a program manager who uses Project Server 2013 and Project Professional 2013. You have administrative rights. Your project managers create subprojects for your program-level master project. You insert the subprojects into your master project file by using Project…

The IT department uses Project Online to analyze the projects they will execute the next year. Four projects with their respective priority and costs are shown in the exhibit. The team needs to get the most value from their portfolio,…

An organization has performed a portfolio analysis in Project Server 2013 by defining a list of drivers and establishing the prioritization for next year’s portfolio. You are finalizing the second quarter for the next year, which is when changes to…