Home » Microsoft » 70-498 » What should you do?
You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint.
You need to conduct a retrospective meeting prior to planning the next sprint.
What should you do?
A. Select items from the product backlog for the next sprint.
B. Decompose the product backlog items into a set of tasks.
C. Determine which items have been finished on the previous day.
D. Analyze the previous sprint to identify what the team is going to do differently during the next sprint.
Correct Answer: D
Explanation/Reference:
This meeting provides an opportunity for the Scrum Team to inspect themselves and identify what went well and what needs improving. If improvements are identified, the team should create an actionable plan for the next Sprint. Nothing is out of scope during --people, relationships, process, and tools can all be discussed. The Scrum this meeting Team may also decide to adjust its Definition of Done to increase product quality. After the meeting, the next Sprint begins.
Reference: Professional Scrum Development with Microsoft Visual Studio 2012 p.6