What should you do?

You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint.
You need to conduct a retrospective meeting prior to planning the next sprint.
What should you do?
A. Select items from the product backlog for the next sprint.
B. Decompose the product backlog items into a set of tasks.
C. Determine which items have been finished on the previous day.
D. Analyze the previous sprint to identify what the team is going to do differently during the next sprint.