Home » Microsoft » 70-498 » Which three elements should you use?
You are developing release plans for a new software development project.
You need to document a flexibility matrix.
Which three elements should you use? (Each correct answer presents part of the solution. Choose three.)
A. schedule
B. risk mitigation
C. scope
D. cost or resources
E. decision-making authority
F. solution architecture
Correct Answer: ACD
Explanation/Reference:
A Project Flexibility Matrix is a simple but effective tool that helps guide tradeoff discussions on Scope, Resources and Schedule during project definition and planning work. The matrix is used to clarify what constraints are flexible and what project goals must be held.