You have a list of tasks entered into Microsoft Visual Studio Team Foundation Server (TFS) 2012. Each task has an estimated effort and assigned to a team member.
You have limited resources available. Due to external requirements, the start date and end date of the current iteration are fixed. Several of the tasks have dependencies on one another.
You need to identify a critical path.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:
Correct Answer:
Explanation/Reference:
* Step 1:
You can communicate with Visual Studio Team Foundation Server by using Microsoft Excel or Microsoft Project. You can start work from Team Explorer, Excel, or Project. Your worksheet or project plan can be tied to a list of work items or a work item query.
* Step 2: Task constraints and dependencies
Team Foundation Server: Tracks predecessor-successor dependencies as work item links for context, but it does not track dependency types, lead and lag time, or work item constraints.
Recommended actions: Use Microsoft Project to manage and update changes to dependencies and constraints.
* Step 3: Use the Team System Gantt view to schedule work in your team project in order to view Team Foundation fields. This split view adds some of the Team Foundation fields to the Microsoft Project Gantt Chart view and changes some Microsoft Project field names to the field names that Team
Foundation uses. It is the default view when you first open work items in Microsoft Project.
Reference: Work in Microsoft Excel and Microsoft Project connected to Team Foundation Server
Quick Tips and Operational Differences when Tracking Tasks Using Microsoft Project and Team Foundation