A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the following is the project a part?

A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the following is the project a part?
A. Project management office
B. Portfolio
C. Program
D. Mission statement