Home » CompTIA » PK0-004 v.3 » Which of the following processes is the project manager performing?
A project manager is developing a network diagram to understand the flow of a project. Which of the following processes is the project manager performing?
A. Defining activities
B. Estimating activity resources
C. Developing a schedule
D. Sequencing activities
Correct Answer: D
Explanation/Reference:
Explanation:
Reference: https://www.futurelearn.com/info/courses/time-management-projectmanagement/0/steps/136200#:~:text=Sequence%20Activities%20is%20the%20process,project%20team%20work%20more%20efficiently.&text=That%20way%20I%20can%20move,them%20in%20a%20logical%20order