Which of the following elements should the project manager have at the end of the meeting?

A project manager is collecting work package information from the project team for the first time.
Which of the following elements should the project manager have at the end of the meeting?
A. Task name, duration, and dependencies
B. Task leveling, baseline, and critical path
C. Task assignments, quality requirements, and project governance sign-off
D. Task start, finish, and estimate cost