Which of the following documents focus primarily on support activities after the completion of a project?

Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)
A. Warranty
B. SLA
C. Purchase order
D. Letter of intent
E. RFQ
F. IMS