Which of the following is the BEST risk strategy to adopt?

A project management team is discussing a potential risk event that would be devastating to the organization and prohibitively expensive to mitigate or insure against if it occurred. Which of the following is the BEST risk strategy to adopt?
A. Accept
B. Exploit
C. Transfer
D. Avoid