Which of the following should the project manager increase to BEST resolve this issue?

A project manager is reviewing a project’s status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks.
Which of the following should the project manager increase to BEST resolve this issue?
A. Resources
B. Quality
C. Schedule
D. Scope