Which of the following would the project manager most likely do NEXT?

A project manager has gathered time estimates for a new project’s activities and is now ready to begin developing the schedule.
Which of the following would the project manager most likely do NEXT?
A. Create a WBS.
B. Determine predecessors and dependencies.
C. Determine the critical path.
D. Prioritize tasks.