Which of the following should the project manager do FIRST?

A customer added an additional requirement for a product being developed. Which of the following should the project manager do FIRST?
A. Present the change request to the CAB.
B. Evaluate the change with the project team.
C. Set up a face-to-face meeting with the project sponsor
D. Organize a steering committee meeting.