Which of the following steps should the project manager take NEXT?

A project team member has completed an assigned task on time.
After updating the project schedule, which of the following steps should the project manager take NEXT?
A. Send an updated schedule to the CCB.
B. Send a project status update to the sponsor.
C. Release the team members to the functional manager.
D. Notify the team members to begin successor tasks.