A recent change request was implemented with approval; however, it had an unforeseen negative impact on the critical path. Which of the following measures should be taken to ensure the project is not delayed?
A. Evaluate the impact of the change.
B. Execute the regression plan.
C. Identify and document the root cause of the issue,
D. Validate the change was quality checked.