A project manager needs to evaluate a suggested change order for a scope enhancement from a vendor on a project. To which of the following documents should the project manager refer?

A project manager needs to evaluate a suggested change order for a scope enhancement from a vendor on a project. To which of the following documents should the project manager refer?
A. RFI
B. PO
C. RFQ
D. SOW