The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
A. Ahead of schedule and over budget
B. Behind schedule and under budget
C. Ahead of schedule and under budget
D. Behind schedule and over budget
CPI less than 1.0 = over budget……BAD
CPI more than 1.0 = under budget……GOOD
SPI less than 1.0 = behind schedule……BAD
SPI more than 1.0 = ahead of schedule…….GOOD
answer is A. period