Which of the following describes the project status?

The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
A. Ahead of schedule and over budget
B. Behind schedule and under budget
C. Ahead of schedule and under budget
D. Behind schedule and over budget

comptia-exams

0 thoughts on “Which of the following describes the project status?

  1. CPI less than 1.0 = over budget……BAD
    CPI more than 1.0 = under budget……GOOD
    SPI less than 1.0 = behind schedule……BAD
    SPI more than 1.0 = ahead of schedule…….GOOD

    answer is A. period