Which of the following documents should the PM provide to the functional manager?

A major project task involves purchasing and implementing computer equipment with special software, which is valued at $1.5 million, for a 700-employee organization. An IT department manager challenged the PM’s ability to authorize expenditures after the purchase was made.
Which of the following documents should the PM provide to the functional manager?
A. Organizational chart
B. Project charter
C. Cost management plan
D. Change management plan