Two team members are discussing the lessons learned from the last testing release. Many quality defects were not reported, and the progress report is not accurate. Which of the following phases/activities are being executed?
A. Planning/governance
B. Monitoring/performance measuring
C. Closing/gathering lessons learned
D. Executing/performing project team