Which of the following techniques is this an example of?

To maintain an active project’s progress, the project manager does not acknowledge any opposing input that was provided.
Which of the following techniques is this an example of?
A. Mitigating
B. Negotiating
C. Forcing
D. Avoiding
E. Accepting