Which of the following would be the BEST solution to meet the project’s timeline?

A project manager, who is overseeing a project in a functional environment, lost two project team members to other projects. The project manager does not anticipate getting any replacements for the remaining duration of the project.
Which of the following would be the BEST solution to meet the project’s timeline?
A. Announce to project team members they will crash the project.
B. Work with stakeholders to reduce deliverable quality.
C. Inform the organization’s management there will be a delivery delay.
D. Negotiate with the project sponsor to reduce the scope of the project

comptia-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.