Which of the following should the project manager do NEXT?

A vendor specifies several enhancement options in a project’s SOW. The project manager receives approval for a budget increase to proceed with the enhancements. Which of the following should the project manager do NEXT?
A. Identify the approval authority.
B. Identify and document the change.
C. Evaluate the impact of the change.
D. Communicate to the project team.