You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00. You need to view graphically which tasks…

You are a project manager for a company that uses baselines in Project Standard 2013. Project stakeholders approve an update to the baseline of a project in progress. You enter the new tasks necessary to include the project schedule changes.…

You are a project manager who uses Project Standard 2013. You regularly customize the Bar Styles for a project prior to printing the project schedule. You need to add the Bar Styles button to the Quick Access Toolbar as quickly…

You are a project manager who uses Project Standard 2013. You manage a large project and are capturing actual work for the tasks as they are being worked. You do not need to enter the time on the actual day…

You are using Microsoft Project Professional 2013. Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a similar project again. You still have the project…

You are a project manager who uses Project Professional 2013. A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom field named CF1 in the…

You are a project manager who uses Project Professional 2013. You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode. What should you do? A. For each new project, use…

You are a project manager who uses Project Standard 2013. A colleague sends you a Microsoft Excel file that contains a list of tasks that define a project you must complete. You need to create a project file that contains…

You are a project manager who uses Project Professional 2013. You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar. You need to assign the weekend working…

You are a project manager who uses Project Standard 2013. Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned…