What should you do?

You are a project manager for a company that uses Project Professional 2013.
You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.
You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.
What should you do?
A. Go to the Task tab, open the Find window, and set the parameters to find the required dates, setting the Look in Field to Finish. Then click Find Next.
B. Go to the View tab, open the More Views window, and create a new view.
C. Go to the View tab and use the Date Range filter.
D. Go to the View tab and select Display AutoFilter. Click on the arrow next to the Finish column and check only the required dates.