What do these variance values mean?

You are a manager for an organization that uses Project Professional 2013.
A critical project shows average finish variance values between 5-10 days for the tasks.
You need to interpret these variance values to determine the next course of action to take.
What do these variance values mean?
A. The project is on schedule.
B. The project is running between 5-10 days ahead of schedule.
C. The project is running between 5-10 days behind schedule.
D. The project is averaging a normal performance timeline.