What should you do?

You are a project manager who uses Project Professional 2013.
You manage a critical project, which involves many team members. You are the only team member who has Project Professional 2013. You need to receive updates from team members directly from Microsoft SharePoint without having to reenter the updates in your project.
What should you do?
A. Set up your project to sync with a SharePoint Task List.
B. Save your project as an mpp file to a SharePoint Shared Documents library.
C. Copy and paste all tasks into a Microsoft Excel file saved in SharePoint.
D. Copy and paste all tasks into a new SharePoint Task List.