Which three actions should you perform in sequence?

DRAG DROP
You are a project manager who uses Project Standard 2013.
Your project is approved, and you identify named resources to replace the generic resources for your project tasks.
You need to update the project schedule to assign the named resources to their appropriate tasks.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place: