What should you do?

You are a project manager for a large telecommunications company that uses Project Professional 2013.
The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.
You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.
What should you do?
A. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Start.
B. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Prorated.
C. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to End.
D. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 1. Change Fixed Cost Accrual to Start.