What should you do next?

You are an independent project manager who uses Project Professional 2013.
You work in multiple projects for different customers and use one project to manage all their tasks. You create a custom field called Customer Name to identify the customer, and you use the Cost field to monitor the amount of money for each task.
You need to view the most expensive detail tasks in the top of your table without subtotals and summaries.
You turned off summary tasks. What should you do next?
A. Set the Sort by option to Cost Descending.
B. Create a custom group based on Cost and Customer Name fields. Define a group by Cost with order as ascending.
C. Set the Sort by option to Cost Ascending.
D. Create a custom view based on Cost and Customer Name fields. Define a group by Cost with order as descending.